Apr 13Blog #8The main parts of the new second iteration of the 3d printed casing have now been printed and assembled. This new device is now fully...
Mar 21Blog #7We have completed a lot of validation and we have attempted some percent accuracy validation with HYTORC. Values for the battery life and...
Feb 17Blog #6For the work period of Feb. 4th to the 17th, preparations are underway for validation of the device, the MATLAB application is in the...
Feb 3Blog #5Over the winter, from December to current, the team focused on producing a functional physical prototype. The CAD files made during the...
Nov 25, 2023Blog #4Between November 11th and 25th, a lot was done in terms of analysis. Our team possessed a broad concept of our design's appearance, yet...
Nov 11, 2023Blog #3The first item of concern right now is the work the team’s done through 10/28 to 11/11. Most notably, CAD drawings of the solution have...
Sep 30, 2023Blog #2As discussed in the previous blog post, we plan on looking at issues concerning bolt monitoring, and most of our reasoning in terms of...
Sep 9, 2023Blog #1Structure monitoring is very important, and current methods sometimes fall short. Bolt monitoring can be difficult to successfully do via...